Builder Scheduling for Ordering Cultured Marble Products

When ordering tubs and/or shower pans

Timing: AFTER framing is finished ( PERMANENT STAIRS MUST BE IN), BEFORE plumbing rough

If the master bath is on the FIRST floor:

Is the second floor fully framed?

If NO, action by

Framer

Have the braces been removed?

If NO, action by

Framer

Has the window in the tub area been framed in full?

If NO, action by

Framer

If on a slab, did the plumber install his booth around drain?

If NO, action by

Framer

If the master bath is on the SECOND floor:

Are the PERMANENT stairs installed?

If NO, action by

Framer

Has the LANDING been built?

If NO, action by

Framer

Is the ROOF fully decked

If NO, action by

Framer

Has the WINDOW been framed in?

If NO, action by

Framer

Access to the house:

Is the house accessible from either garage or front door (no drop off coming out of the house)

If NO, action by

Framer

When ordering shower walls and vanity tops

TIMING: AFTER priming of the walls

If NO, action by

CABINET CO.

If NO, action by

CABINET CO.

Are the vanity bases fully installed?

 

Have the cabinet braces been cut to allow for bowl to fit?

If NO, action by

BUILDER

Has the shower pan and tub been drained of water and other fluids?

NO double sheetrock on master shower?

If NO, action by

BUILDER

IF hall tub surrounds needed, SINGLE sheetrock only?

If NO, action by

BUILDER

Will painters be finished?

If NO, action by

BUILDER

Are we scheduled BEFORE or AFTER tile install (NOT DURING)?

Contact Imi

When ordering "skirt" (tub front) and trim

TIMING: CHECK if bathroom will get tile or carpet

If carpet tub front to go in preferably PRIOR to carpet install

If tile tub front to go in AFTER tile install

Is tile ran 2" past tub lip towards the tub bowl?

If NO, action by

TILE CO.

Make sure plumbing is HOOKED UP

If NO, action by

PLUMBER

Make sure plumbing is NOT protruding past the tub lip

If NO, action by

PLUMBER

When ordering "pedestal" for powder rooms

TIMING: AFTER first coat on hardwoods or tile is in

Do hardwoods have at least one coat on?

Schedule with IMI

Will plumber install pedestal or IMI?

 

eMail International Marble Industries Contact Sales
Call International Marble Industries 770.928.2252


eMail International Marble Industries Contact Customer Service


eMail International Marble Industries Contact Accounting


Contractor Tools Contractor tools

Contractor Tools Kitchen and Bath dealers

Download your contractor kit (PDF)

Request an on-site showing (cabinet dealers only)
Email Newsletter icon, E-mail Newsletter icon, Email List icon, E-mail List icon Sign Up Here For IMI's Email Newsletter, Including Special Offers For Subscribers Only!
For Email Marketing you can trust